    Based on certain technological process, by designing and calculating the main size, pipe diameter selection and hydraulic loss of the structure (including grille, vortex grit chamber, A/O biological pond, horizontal flow sedimentation tank, sludge concentration pool), we complete the design of the process flow diagram (including top arrangement), the factory layout and the design of the main body structure of monomer figure.
    The project investment cost is 182.22million yuan, which is technically feasible and economically reasonable. The process operation is simple, high degree of automation, operation and management cost is relatively low, sewage treatment cost is 0.25 yuan/m3;The whole process with a total investment is reasonable, stable operation and less secondary pollution, good processing effect, and low energy consumption, and achieve the tail water discharge standards.
    After waste water processing, CODcr≤100mg/L;BOD5≤30mg/L;SS≤30mg/L; NH3-N≤5mg/L;TP≤3mg/L, which meet the secondary emission standard of  "the urban sewage treatment plant pollutant discharge standard "(GB18918-2002).So that the contaminated water quality have greatly improved, which eliminate the pollution , achieve the purpose of protecting the environment and make the benefit of human.
    Key Word: effluent treatment; A/O; activated sludge;
     目 录
    1 绪论    1
    1.1 概况    1
    1.2 设计依据与原则    1
    1.2.1 设计依据    1
    1.3 设计规模和目标    2
    2污水处理工艺的选择    3
    2.1 沉砂池比较    3
    2.2主体工艺的选择    3
    2.1.1 传统活性污泥法处理工艺    3
    2.1.2 生物接触氧化法处理工艺    4
    2.1.3 AB法处理工艺    4
    2.1.4 A2/O法处理工艺    5
    2.1.5 A/O法处理工艺    6
    2.1.6 各工艺之间比较    7
    2.3二沉池的选择    7
    2.4总工艺流程    8
    2.5预期处理效果    9
    3工艺说明    9
    3.1 工艺说明    9
    3.1.1 格栅    9
    3.1.2 旋流沉砂池    10
    3.1.3 生物池    10
    3.1.4 平流式沉淀池    10
    3.1.5 污泥浓缩池    11
    3.1.6 紫外线消毒池    11
    3.1.7 污泥泵房    11
    3.1.8 污泥处理    11
    3.2 设计计算    12
    3.2.1 格栅设计    12
    3.2.2 旋流沉砂池    16
    3.2.3 A/O池    18
    3.2.4 曝气池    22
    3.2.5 平流式沉淀池    25
    3.2.6 污泥浓缩池    28
    3.2.8 管道设计    31
    3.2.9 污水厂区高程计算    32
    3.2.10 土建费用及主要设备材料费用    34
    3.2.11 运行费用    35
    3.3环境保护、建筑防火和职业安全防护    36
    3.3.1环境保护    36
    3.3.2 厂区绿化    37
    3.3.3 建筑防火    38
    3.3.4 职业安全防护    38
    4 结论与建议    38
    5参考文献    40
    6致谢    42
    附录    43
    1 绪论
    1.1 概况
    现今中国对污水的治理力度越来越强,每一年都有相当数量的污水处理厂和企业内的设施设备进行规划,更新,制造并用于实际生活中。本课题的设计对象是主要用来处理洋浦港和虹口港这两个地区产生的生活及工业污水的污水处理厂,厂址位于上海东北部,总面积达到310亩,每天的污水处理量大约为50万吨,属于超大型规模。根据资料显示,这两个港口总计有13个排水系统地区,其虹口港流域和杨浦港流域几乎各半。
  1. 上一篇:每天5000立米生物制药废水的处理工艺设计+CAD图纸
  2. 下一篇:日处理5万吨城镇生活污水的工艺设计+CAD图纸
  1. 年产50万吨乙二醇项目厂址选择与经济分析

  2. 某校化工实验室安全隐患检查及对策

  3. 某校化学楼115室安全调查与建议

  4. 某校化学楼113室安全调查与建议

  5. 徐州市日处理3000吨某小区...

  6. 某化工废水处理实验

  7. 某城镇印染专业基地废水...

  8. 当代大学生慈善意识研究+文献综述

  9. 乳业同业并购式全产业链...

  10. java+mysql车辆管理系统的设计+源代码

  11. 大众媒体对公共政策制定的影响

  12. 河岸冲刷和泥沙淤积的监测国内外研究现状

  13. 中考体育项目与体育教学合理结合的研究

  14. 十二层带中心支撑钢结构...

  15. 电站锅炉暖风器设计任务书

  16. 酸性水汽提装置总汽提塔设计+CAD图纸

  17. 杂拟谷盗体内共生菌沃尔...

  

About

751论文网手机版...

主页:http://www.751com.cn

关闭返回