菜单
  

    Bond strength tests were conducted by means of a hand operated hydraulic jack and a custom-built test rig as shown in Fig. 3. The loading scheme is illustrated in Fig. 4. A plastic tube of length 80 mm was provided at the end of the concrete section underneath the transverse reaction to ensure that the bond strength was not enhanced by the reactive (compressive) force (acting normal to the bar). The specimen was positioned so that an axial force was applied to the bar being tested. The restraints were sufficiently rigid to ensure minimal rotation or twisting of the specimen during loading.
     
    Fig. 3 Pull-out test, 16 mm bar unconfined
     
    Fig. 4 Schematic of loading. Note: only test bar shown for clarity


    3   Experimental results and discussion

    3.1   Visual inspection
    Following the accelerated corrosion phase each specimen was visually inspected for the location of cracks, mean crack width and maximum crack width (Sect. 2.3).
    While each specimen had a mean target crack width for each bar, variations in this crack width were observed prior to pull out testing. This is due to corrosion and cracking being a dynamic process with cracks propagating at different rates. Thus, while inpidual bars were disconnected, once the target crack width had been achieved, corrosion and crack propagation continued (to some extent) until all bars had achieved the target crack width and pull out tests conducted. This resulted in a range of data for the maximum and mean crack widths for the pull out tests.
    The visual inspection of the specimens showed three stages to the cracking process. The initial cracks occurred in a very short period, usually generated within a few days. After that, most cracks grew at a constant rate until they reached 1 mm, 3–4 weeks after first cracking. After cracks had reached 1 mm they then grew very slowly, with some cracks not increasing at all. For the confined and unconfined specimens the surface cracks tended to occur on the side of the specimens (as opposed to the top or bottom) and to follow the line of the bars. In the case of the unconfined specimens in general these were the only crack while it was common in the cases of confined specimens to observe cracks that were aligned vertically down the side—adjacent to one of the links, Fig. 5.
     
    Fig. 5 Typical crack patterns
    During the pull-out testing the most common failure mode for both confined and unconfined was splitting failure—with the initial (pre-test) cracks caused by the corrosion enlarging under load and ultimately leading to the section failing exhibiting spalling of the top corner/edge, Fig. 6. However for several of the confined specimens, a second mode of failure also occurred with diagonal (shear like) cracks appearing in the side walls, Fig. 7. The appearance of these cracks did not appear to be related to the presence of vertical cracks observed (in specimens with stirrups) during the corrosion phase as reported above.
     
    Fig. 6 Longitudinal cracking after pull-out
     
    Fig. 7 Diagonal cracking after pull-out
    The bars were initially (precasting) cleaned with a 12% hydrochloric acid solution, then washed in distilled water and neutralized by a calcium hydroxide solution before being washed in distilled water again. Following the pull-out tests, the corroded bars were cleaned in the same way and weighed again.
    The corrosion degree was determined using the following equation
     

    where G 0 is the initial weight of the steel bar before corrosion, G is the final weight of the steel bar after removal of the post-test corrosion products, g 0 is the weight per unit length of the steel bar (0.888 and 1.58 g/mm for Φ12 and Φ16 mm bars, respectively), l is the embedded bond length.
    Figures 8 and 9 show steel bars with varying degree of corrosion. The majority exhibited visible pitting, similar to that observed on reinforcement in actual structures, Fig. 9. However, a small number of others exhibited significant overall section loss, with a more uniform level of corrosion, Fig. 8, which may be a function of the acceleration methodology.
  1. 上一篇:IOS APP Store英文文献和中文翻译
  2. 下一篇:Servlet与JSP技术英文文献和中文翻译
  1. 接头的形状对沥青塞接头...

  2. 对热流道系统注塑工艺英文文献和中文翻译

  3. 预制板的连续组合双肋桥...

  4. 知识管理及其对隐性知识...

  5. 对木桥的负载和阻力系数...

  6. 在平衡的轴向荷载下K型管...

  7. 水泥用量对暴露在高温下...

  8. 河岸冲刷和泥沙淤积的监测国内外研究现状

  9. 酸性水汽提装置总汽提塔设计+CAD图纸

  10. 中考体育项目与体育教学合理结合的研究

  11. java+mysql车辆管理系统的设计+源代码

  12. 杂拟谷盗体内共生菌沃尔...

  13. 大众媒体对公共政策制定的影响

  14. 电站锅炉暖风器设计任务书

  15. 十二层带中心支撑钢结构...

  16. 乳业同业并购式全产业链...

  17. 当代大学生慈善意识研究+文献综述

  

About

751论文网手机版...

主页:http://www.751com.cn

关闭返回